Another update!

Things are still moving ahead full speed and we are looking at moving in around the first of December! This week the landscaping was pretty much finished up, parking lot striped, cabinets are being installed in the offices, bought a new to us milling machine and lathe, main lift to second floor is partially installed, fencing is going up, etc…

Unfortunately the flooring has been delayed and is now several weeks late. Luckily though, it is in the country at this point and is finally leaving the distributor on a truck headed for us tonight. They forgot to ship the glue to the US so we are going to be waiting on that a little longer. More to come very soon!

Oh and I’m adding trillions of products to the new online store as we speak and plan to go live with that when we open the new store. More updates on the way for that as well.

The rest of this flickr photo set can be seen here.

Front landscaping mostly complete.

IMG_1597.JPG

Another view of the front.
IMG_1601.JPG

Building painted, landscaping going in.
IMG_1603.JPG
 
Ed’s row all planted.
IMG_1602.JPG
 
A visitor, anyone know what it is?
IMG_1604.JPG
 
New toy just delivered and being cleaned up by Kenneth.
IMG_1607.JPG
 
New lift to second floor being installed.
IMG_1606.JPG
 
Cabinets being installed in office.
IMG_1611.JPG

0 Responses to “Another update!”


  1. No Comments

Leave a Reply